Being ready to request a quote is different from being ready to sign a contract or bring a construction team onto site. Each decision needs its own evidence. Sending concept drawings to a contractor does not establish the quantities, delivery arrangements or material responsibilities needed to start work.
Use the following checklist to assess one stage at a time. Record each unresolved item with an action owner, deadline and the evidence needed to close it. If you manage the project from outside Bali, appoint a local contact with written authority limits. A photograph in a progress report is not, by itself, approval for work or payment.
1. Before requesting quotes
Agree the owner's brief and budget limits
Check: how the home or villa will be used, the rooms required, occupants' needs, quality priorities, target opening or move-in date, and work that could be deferred. Separate the main works budget from owner purchases, professional fees and a risk contingency. Record outstanding choices, such as finishes or fittings.
Who follows up: the owner agrees the brief with the designer. An owner's representative consolidates decisions when the owner is away from Bali.
Evidence of readiness: a dated brief, budget limits, ranked priorities and a named person authorised to approve changes. All bidders should receive the same instructions.
Review the land and the delivery route
Check: site boundaries and conditions, levels, visible drainage routes, utilities, neighbouring buildings and areas that could not be inspected. Measure narrow sections, bends, turning space, unloading points and the route from the vehicle to the work area. Confirm use of the access with the parties entitled to authorise it.
Who follows up: the site coordinator arranges a survey with the designer and prospective contractor. Questions about land, structural design or ground conditions go to the appropriate professionals; a visual visit alone cannot settle them.
Evidence of readiness: dated survey notes and photographs, access measurements, an agreed unloading point and a list of missing information. Any limitation that could affect pricing belongs in the request for quotation.
Align drawings, specifications and scope
Check: whether the drawings are detailed enough for the package being priced, materials are identifiable and the boundaries between each party's work are clear. Distinguish concept drawings from documents approved as the pricing basis. Flag quantities that cannot yet be established.
Who follows up: the designer resolves design questions; the estimator aligns quantities and scope. The owner approves the package boundaries.
Evidence of readiness: a document register with revision numbers, specifications, inclusions, exclusions and a common assumptions list. If information is incomplete, label an early quote as indicative and explain its limits before treating it as a final price.
2. Before signing the contract
Reconcile the quote with the project documents
Check: that every bidder used the same drawing and specification revisions. Look for work shown but not priced, duplicated items, alternative materials and items marked “by owner” with no clear person responsible.
Who follows up: the owner or representative requests written clarifications. The designer resolves technical discrepancies and the contractor revises the quote.
Evidence of readiness: a revised offer and clarification schedule incorporated into the agreement. To decide who should procure materials, use the worked comparison of labour-only and labour-and-materials costs. Choose the procurement arrangement once the work boundaries are comparable.
Allocate responsibilities and contingency
Check: who buys, delivers, receives, stores and checks materials; who provides tools, temporary utilities and protection for adjacent areas. Agree how shortages, damage and substitutions will be handled. Have each bidder state its tax treatment without assuming a rate.
Who follows up: the owner and contractor prepare a responsibility schedule. The person preparing the budget helps identify the project risks that need contingency funding.
Evidence of readiness: an agreed responsibility schedule and a budget separating the contract sum, costs outside the contract and contingency. The owner controls the contingency; its existence does not authorise additional work. Set the allowance from identified risks rather than assuming one percentage suits every project.
Test the programme, change process and payment terms
Check: the links between design approvals, ordering, deliveries, work sequencing and inspections. Identify who assesses a proposed change and approves its cost and time effects before execution. Link payment stages to verifiable evidence, as well as any agreed dates.
Who follows up: the contractor prepares the programme and decision requirements. The owner agrees response deadlines, the representative's authority limits and a written approval process.
Evidence of readiness: an agreed programme, change procedure and payment schedule stating the trigger for each claim, supporting evidence, reviewer and approver. Overseas owners should also agree communication windows and a substitute decision-maker for periods of unavailability.
Fictional example: the delivery truck cannot reach the site
On a fictional villa project, a survey finds that the supplier's truck cannot negotiate the final bend. A smaller vehicle can enter, but a transfer point has not yet been agreed. This is an illustration, not a BPP client project.
Before quotes are requested, the coordinator records the bend dimensions and asks the supplier to confirm a suitable vehicle. Before contract signing, the contractor states whether the price includes transferring loads, extra journeys, unloading labour and responsibility for damage during handling.
A delivery originally assumed to take one trip may require several trips and waiting time. Vehicle and labour costs can increase, while staggered material arrivals may change the work sequence. This example does not establish a specific extra cost or delay: request a logistics quotation and an updated programme.
Before mobilisation, confirm the transfer point, relevant access permissions, receiving contact and delivery times. Do not schedule the installation team on the assumption that all materials will already be there.
3. Before mobilisation
Confirm access, storage and the first materials
Check: that the access plan will work on the start date, unloading can be managed safely, storage suits the materials, and the first activities have the necessary materials and tools. Check order status and supplier confirmations. A shopping list does not prove goods are ready for dispatch.
Who follows up: the contractor checks the work area. Whoever purchases the materials confirms delivery; the nominated receiver records quantities, condition and discrepancies on the delivery note.
Evidence of readiness: a site checklist, storage photographs, delivery confirmations, materials allocated to the opening sequence and a procedure for short or damaged deliveries.
Confirm contacts and document status
Check: contacts for the owner, owner's representative, designer, contractor's lead, material receiver and emergency response. Record the status of working drawings, land documents, design approvals, execution documents and relevant permits or permissions individually.
Use three distinct statuses:
- Not available: there is no document to inspect; name the person responsible for obtaining it and a deadline.
- Received, not confirmed: a file exists, but its revision, coverage or approval has not been verified.
- Confirmed: identify the document, revision, date, reviewer or approving party, and confirmation evidence.
Who follows up: the coordinator maintains the register. The owner, designer, contractor or relevant specialist closes each item within their authority. Confirm which permits are needed, which authority is responsible and the approval status for this particular location and scope. This article does not prescribe a universal permit list.
Evidence of readiness: an up-to-date contact list and document register with supporting evidence. An item described as “being processed” remains open. Hold activities that depend on unconfirmed access, approvals or essential documents, and distinguish them from preparatory tasks that can lawfully and safely proceed.
FAQ
Are concept drawings enough to request quotes?
They can support an initial budget discussion if their limitations are clear. Quotes intended to support a contract need drawings, specifications, quantities and scope boundaries detailed enough for the package concerned.
Who decides whether the project is ready to start?
The owner makes the decision using evidence from those responsible for each discipline. Technical readiness and specialist approvals must still be confirmed by the appropriate authorised parties; an owner's commercial decision cannot replace them.
How can an owner manage this from outside Bali?
Appoint a local contact, set approval limits for spending and work, and maintain a shared document and decision register. Request site evidence tied to specific areas, dates and work items so that reports lead to clear actions.
Must every open item be closed before moving on?
Close the prerequisites for the next stage first. A finish needed much later may be selected later, with a deadline before ordering. An unresolved item affecting safety, authority to proceed or the opening works needs more than a verbal assurance.
Support with the readiness decision
BPP's pre-construction risk review can help identify information gaps, action owners and priorities before mobilisation. It does not guarantee a trouble-free project or replace specialist professional decisions.
Discuss your project's readiness with BPP. Share the location, current stage, available drawings, intended start date and known constraints so the review requirements can be discussed.
Final checklist: ready to proceed or not yet?
- Before quotes: the brief, access conditions, drawing revisions, specifications and scope form a common basis for pricing.
- Before signing: discrepancies are closed, and responsibilities, contingency, programme, changes and payment terms are recorded.
- Before mobilisation: access, storage, initial materials, contacts and prerequisite documents and approvals are confirmed.
- For each open item: identify an action owner, deadline, required evidence and whether it blocks the next stage.
Ready to proceed means the evidence is sufficient for that stage and the next activities have clear boundaries. Not yet ready means an essential prerequisite remains unconfirmed; close it and reassess before instructing the team to proceed.